Kazungula Water Supply and Basic Sanitation Project

SCOPE

Construction of a new water intake approximately three kilometres upstream the new bridge, Construction and installation of 200kW PV solar plant, Construction of a 5.7 Kilometres 11KVA power line from the treatment plant to the new intake, Expansion of the Water Treatment Plant to increase capacity, Rehabilitation and extension of water distribution pipes, Construction of water reservoirs and storage facilities.

LOCATION

Kazungula

STATUS

15%

PERIOD

Dec 2022 to Aug 2024

BUDGET

Euros 5,991,006.94

FUNDER

KfW